Design Activity For Removal Overburden In Coal Mining PIT M Middle Roto Pt Bukit Makmur Mandiri Utama Batu Sopang Subdistrict, Paser District East Kalimantan Province

Mohammad Rifki Hardiyono, Dono Guntoro, Yuliadi Yuliadi

Abstract


The study was conducted at PT Bukit Makmur Mandiri Utama jobsite KIDECO
located in District Batu Sopang, Paser Regency, East Kalimantan Province. The
purpose of this study is to design activities of overburden stripping which are from
loader unit selection, sequence of mining, as well as the design of tool pair (fleet) which
is based on a target production in May 2015 of 277,608 tonnes of coal and overburden
2,612,778 BCM with a stripping ratio of 1: 9.41.
In May 2015 plan 7 loader units consisting of 2 units of Komatsu PC 4000, 1
unit of Hitachi EX 3600, 2 units of Komatsu PC 2000 and 2 units of PC 1250 are set up
with a total production capacity of 2,903,219.71 BCM/Month.
Designing the sequence of mine in May divided over 7 locations in accordance
with the number of loading tool and production capacity, which cutback in is aimed to
strip from the east and south locations of pit M with the purpose to expose the coal
seams of 15,16, and 17 which are the upper east side. Cutback is also aimed to strip
on the east side of the middle and lower south pit which is aimed in time until the
decreasing elevation to get the coal seams of 12. The results of the mining sequence
using the reserve minescape software version 4.118 extract tons of coal 300,456.05
with recovery of 90% and 2,725,524.31 BCM overburden with SR 1 :9.07. Based on
data coal price in January 2016 the calculation result BESR (economic) stripping ratio
1:3,1 is obtained, so that be needed reducing distance transportation to save the cost
overburden stripping.
To perform the removal of overburden material to the disposal site M pit area
located in the south of Pit M, then the design of the tool pair (fleet) in stripping
overburden is based on data obtaining use 7 fleet. To gain the purpose is carried by
using three types of hauler of Caterpillar OHT 789 C, Caterpillar 785 D and Komatsu
HD OHT 785.

Keywords


overburden, fleet, sequence, stripping ratio

References


Anonim (a). 1993. AASHTO Guide for Design of Pavement Structures—Volume I, Washington, DC.

Anonim (b). 2014. Kabupaten Paser Dalam Angka. Badan Perencanaan Pembangunan Daerah Kabupaten Paser. Tanah Grogot.

Anonim (c). 2012. Caterpillar Performance Handbook. Edition 41. Catterpilar

Anonim (d). 2009. Specifications & Application Handbook. Edition 30. Komatsu Inc.

Call, R.D. 1986. Cost Benefit Design Of Open Pit Slopes. In: 1st Open Pit Mining Symposium, Antofagasta, Chile, October 1986: 1-18

Couzens, T.R. 1979. Aspects Of Production Planning: Operating layout and phase plans. In: Open Pit Mine Planning and Design (J.T. Crawford andW.A. Hustrulid, editors): 217-232. SME.

Hidayat, S, Umar, L, 1994, Peta Geologi Lembar Balikpapan. Kalimantan. Pusat Penelitian dan Pengembangan Geologi.

Hustrulid, W., Kutcha, M., & Martin, R. 2006. Open Pit Mine Planning Design 3rd Edition. CRC Press. London.

Kaufman, W.W., & J.C. Ault. 1977. Design of Surface Mine Haulage Roads - A Manual. USBMIC 8758.

Monenco. 1989. Design Manual for Surface Mine Haul Roads. Draft report by Monenco Consultants Limited, Calgary, Alberta.

Peurifoy, R. L., 1970, “Construction, Planning, Equipment and Methodsâ€, Second Edition, Mc Graw-Hill, Kogakusha Ltd, Texas

Prodjosumarto, P. 1993. Pemindahan Tanah Mekanis. Jurusan Teknik Pertambangan. Institut Teknologi Bandung. Bandung

Prodjosumarto, P. 2004. Pengantar Perencanaan Tambang. Universitas Islam Bandung. Bandung.

Ridha, A.H. 2008. Rancangan Penambangan Batubara Studi Kasus Pit Inul Departemen Hatari, PT Kaltim Prima Coal. Tugas Akhir. Institu Teknologi Bandung. Bandung.

Ritchie, A.M. 1963. Evaluation Of Rockfall And Its Control. Highway Research Record 17:13-18

Rohmandi. 1981. Alat-Alat Berat dan Penggunaannya. Badan Penerbit Pekerjaan Umum – Departemen Pekerjaan Umum Republik Indonesia. Jakarta.

Stacey, T.R. 2006. Considerations Of Failure Mechanisms Associated With Rock Slope Instability And Consequences For Stability Analysis. JSAIMM. 106(7): 485-493.

Tannant, D & Regensburg, B. 2001. Guidelines For Mine Haul Road Design. School of Engineering University of British Columbia. Okanagan Kelowna.

Tenriajeng, A.T. 2003. Pemindahan Tanah Mekanis. Gunadarma. Jakarta.




DOI: http://dx.doi.org/10.29313/pertambangan.v0i0.2619